+#+title: Project schedule
+#+date: 2011-05-31
+#+layout: post
+#+category: gsoc
+
+The following is a modification made by my mentors to the original
+schedule found in [[http://www.google-melange.com/gsoc/proposal/review/google/gsoc2011/gnusosa/1][here]]
+
+**** Week #1:April 25 - 23 May
+Gather current Dancer's core, plugin and packaging documentation, and
+study this as an introduction. Arrange the working schedule with the
+mentors based on the observed goals, and schedule a better working
+process based on the timeline.
+
+**** Week #1: 24 - 28 May
+Review and select suggestions from users, developers, and mentors on
+the module. Study the possibilities of the upgrade module, and code a
+rough draft to be worked on.
+
+**** Week #2: 29 May - 4 June
+Finish successfully moving the old script intact to an object oriented
+module. Write tests for the current object oriented module.
+
+**** Week #3: 5 - 11 June
+Study =Catalyst= scripts and =Catalyst::ScriptRunner=, derive a code from
+both to merge to the project.
+
+**** Week #4: 12 - 18 June
+Write the upgrade methods and add tests for those.
+
+**** Week #5: 19 - 25 June
+Add the module to Dancer's core and run it against several outdated
+setups. Review the results and calibrate the tests to the resulting
+patterns.
+
+**** Week #6: 26 June - 2 July
+Add an upgrade log file
+for the upgrade process for outdated Dancer setups.
+
+**** Week #7: 3 - 8 July
+Go over the tests and add any
+missing test to allow extensive coverage.
+
+**** Week #8: 10 - 16 July
+Prepare the Midterm report, describe the status of the project and
+further plans.
+
+**** Week #9: 17 - 23 July
+Document the module, and the config.yml
+
+**** Week #10: 24 - 30 July
+Write a code hand-out of the plugins implementation: How it must work,
+how will it work and for what functions. Add detailed tests to each
+plugin function.
+
+**** Week #11: 31 July - 6 August
+Calibrate and polish the plugin implementations, while tracing each
+test successful output to see what can be added. Write a rough draft
+of the documentation relating the plugin feature.
+
+**** Week #12: 7 - 13 August
+Review the documentation and make it more user-friendly.
+
+**** Week #13: 14 - 22 August
+Finish what was left undone, make sure the tests are well-written, the
+coverage is high and the documentation covers every aspect of the
+project.